Chinese New Year 2027 (6 February): when must the order be placed?

By David RutströmPublished Updated

Chinese New Year 2027 falls on 6 February 2027, and the official holiday runs from 5 February to 13 February.

It is the biggest holiday of the year in China, and it affects every order to be made or shipped around it. What surprises most people is not the holiday itself. It is how long factories stand still around it.

When is New Year 2027?

Chinese New Year 2027 falls on 6 February 2027. The date follows the lunar calendar and so moves between late January and mid-February from year to year.

The official holiday runs from 5 February to 13 February 2027, set by China's State Council. To make up for it, 31 January and 14 February are working days. Source: Beijing Municipal Government, 2027 public holiday schedule (State Council notice of 5 November 2026).

When must the order be placed?

Place the order at least two months before New Year. Ahead of New Year 2027, that means by around 6 December 2026 at the latest.

That is a rule of thumb for an order where tooling and samples are already done. If a mould has to be made, or new sample rounds are needed, start earlier. A mould usually takes 25 to 65 days to make, and production then often around 30 days.

What you want to avoid is an order that is halfway through when the factory closes. It sits, and after the holiday it has to be picked up again by a production line that is not yet back in rhythm.

Why factories stand still longer

The official holiday is only the core. Many factory workers travel a long way to celebrate with family and take more time off than the statutory days. Production winds down in the weeks before, as people start travelling, and restarts slowly afterwards, when not everyone has come back.

It is not just your factory. The suppliers of materials, components and packaging close too. A factory that is open but has no cartons stands still all the same.

At the same time, everyone wants their goods shipped before the holiday. Freight capacity gets tight, prices rise, and goods that miss loading sit until ports and forwarders are running again.

Count back

Start with the date the goods must be with you, and count back:

  1. Subtract the freight. Sea takes longest, air shortest. Expect it to be crowded in the weeks before New Year.
  2. Subtract inspection and packaging.
  3. Subtract production, often around 30 days.
  4. Subtract tooling and sample rounds if they are not done.
  5. If New Year falls anywhere in that chain, add the weeks the factory stands still in practice, and make sure the order is placed at least two months before New Year.

If the start date is already behind you, there are three ways out: ship part of the order by a faster mode, move the launch, or place the order so that production happens after the holiday instead. More on how the time breaks down in the guide how long from drawing to delivery?

Quality before and after

Two periods need extra attention.

The weeks before New Year. Factories want to finish as much as possible before they close. That is when shortcuts are taken: an inspection skipped, a material swapped for whatever is in stock, an order packed in a hurry.

The weeks after. Production restarts, often with staff who are new or have not made your product for a while. The first production after the holiday is the one that most often deviates.

Both are solved the same way: inspect the goods before they ship, against the approved sample and the specification. That is what factory visits and quality control is for.

Stock before and after

What does not ship before the holiday arrives late. Goods leaving the factory in the weeks after New Year first have to be finished, then inspected and loaded, and then shipped. If you sell something with a spring season, outdoor equipment for example, that can mean the goods arrive once the season has already started.

So work out how long your stock has to last, not just when the order must be placed. Stock that lasts until just after New Year is not enough, because the first delivery after the holiday arrives considerably later than that. Build up stock to cover the whole gap, with a margin.

Agree before everyone goes home

During the holiday it is hard to reach anyone, and it is not the moment to sort out a question about material or packaging. Agree with the factory before the holiday what applies: which orders will be finished, which are paused, when production restarts and who the contact is when it does.

Write it down. An agreement that only exists in a call before the holiday is easy to forget after it, especially if the contact person does not come back.

The other holidays

New Year is the biggest, but not alone. National Day on 1 October is followed by a week off, and May Day brings a few days off. They have less effect than New Year, because fewer people travel as far, but they close factories and affect freight in the same way on a smaller scale.

Production that has to be finished in October should be planned with the same logic: what happens if the order is halfway through when the holiday starts? The same rule of thumb applies: better finished before than halfway.

What you can do

  • Place the order at least two months before New Year, and earlier if tooling or samples are not done.
  • Book freight in good time, and use a faster mode for part of the order if time is short. See the guide on sea, rail or air.
  • Make sure packaging and materials are at the factory before the holiday, not after.
  • Inspect the goods before shipping, both before and after the holiday.
  • Do not change supplier just before New Year. The new factory will not get going in time. More in the guide on changing supplier.
  • Build up stock before the holiday so you get through the weeks when nothing ships.

If you want to plan ahead of New Year 2027, we put a schedule together for your order. More on manufacturing and shipping and import.

General information, not legal advice. Always check the current rules with the responsible authority.