How long does it take from drawing to delivery?

By David RutströmPublished

It depends on where you start. Arrive with a finished drawing and a large part of the work is done. Arrive with an idea and it is ahead of you. But the steps are the same, and most take roughly the same time every time. What differs is how many times you go through them.

The phases

From idea to documentation

If you start with an idea, a sketch or a prototype, it first has to become something a factory can quote from. Drawings, supplier selection and a quote take from a few days to a few weeks, depending on how complex the product is and how much is already decided.

The quote

With a finished drawing we usually have a quote within a couple of days. That assumes the drawing is enough: material, dimensions, finish and volume must be clear. If something is missing, questions come back, and every question is a day.

Samples

Before anything is made in volume, samples are made for you to approve. This is where time usually slips, because every round takes time to make, ship and judge. One round may be enough. If the specification is unclear, there will be more.

Tooling

This is where products differ most. Parts that can be made directly, by CNC for example, need no tooling and can start at once. If a mould is needed it usually takes around 25 to 65 days to make, depending on its complexity. After that come trial shots from the mould, and sometimes adjustments.

Production

Once the samples are approved and the tooling is ready, production often takes around 30 days. It depends on volume, the factory’s queue and whether the product has several parts to assemble.

Inspection and packaging

Packaging, labelling and manuals must be ready when production is, so they should be developed in parallel. Inspection before shipping happens when the goods are finished but before they are loaded.

Freight and customs

Sea, rail or air. Sea is slowest, air fastest, and rail in between. On top of the transport itself come loading, customs clearance and onward transport to your warehouse. More in the guide on sea, rail or air freight from China.

A worked example

Two products, both with a finished drawing:

A product that can be made directly by CNC. A quote within a couple of days. One sample to approve. Production often around 30 days. Then inspection, packaging and freight.

A product that needs a mould. A quote within a couple of days. The mould usually takes 25 to 65 days. Trial shots to approve, perhaps an adjustment. Production often around 30 days. Then inspection, packaging and freight.

The difference between the two is the mould, which is why the choice of manufacturing method affects the schedule as much as the cost. If you start with an idea rather than a drawing, add the time for drawings and supplier selection at the front, from a few days to a few weeks.

What stretches it

Most delays can be foreseen. The ones that come back again and again:

  • More sample rounds than planned. Almost always because something in the specification was unclear: a material, a colour, a finish, a tolerance.
  • Changes after the tooling is made. Tooling can be changed, but it takes time, and then new trial shots have to be approved.
  • Packaging at the last minute. The goods are ready but the carton is not printed. It happens more often than you would think.
  • Testing and certification. Done by institutes such as SGS, Intertek and TÜV, and it takes its time. Finding out late that a product needs testing can move a launch more than any other single thing.
  • Holidays in China. Chinese New Year closes factories for several weeks in practice, and the National Day holiday in early October has an effect too. New Year has its own guide.
  • The factory’s queue. A full factory takes your order when it has room, not when you want it to.

Plan backwards

If you have a date that cannot move, a trade fair, a season, a launch with a retail chain, start there and count back:

  1. When must the goods be in your warehouse?
  2. Subtract freight and customs clearance, with a margin.
  3. Subtract production and inspection.
  4. Subtract tooling and sample rounds. Allow for at least one extra round.
  5. Subtract drawings and the quote if you do not have them.
  6. Check whether Chinese New Year falls anywhere in that chain. If it does, place the order at least two months before New Year.

The result is the date the work has to start. If it is already behind you, there are three ways out: a faster freight mode, a simpler manufacturing method for the first order, or a later date. Better to choose now than to find out in August.

What you can do to make it faster

  • Specify properly from the start. It is the single biggest thing that shortens the time, because it cuts the number of sample rounds.
  • Develop the packaging in parallel with the samples, not after.
  • Find out the testing requirements early. If the product needs testing, plan it in from the start.
  • Decide quickly. A sample that sits on a desk for two weeks is two weeks.
  • Place the first order with a margin to peak season and holidays.

What most often decides whether a schedule holds is not the factory but the decision path on your side. A sample that three people in two countries have to approve takes longer than one a single person can approve the same day. Decide in advance who has the final say on samples, colours and packaging.

If you want a schedule for your product, we put one together once we know what you have. The first call is usually enough to see which phases are needed and where the risks are. More on product development, manufacturing and shipping and import, or on what it costs.

General information, not legal advice. Always check the current rules with the responsible authority.